Utilization (Site) KPIs
KPI | Parameter | Description |
Working and Idle Hours |
Long Idle Time |
|
Duration of an asset engaged in idling with no movement for more than nine minutes. |
||
Medium Idle Time |
Duration of an asset engaged in idling with no movement between six and nine minutes. |
|
Short Idle Time |
Duration of an asset engaged in idling with no movement between three and six minutes. |
|
Working Time Percentage
|
Sum of the working duration of the respective site’s assets ÷ Sum of the total duration (working + idle) * 100. Working time is defined as sum of working hours for all assets based on the selected date range and asset tag. Total duration is defined as sum of working hours and substates (long, medium and short idling hours) of all assets based on the selected date range and asset tag. |
|
Idle Time |
Total sum of idling hours (productive + short + medium + long) for all assets based on the selected date range and asset tag.
|
|
Long Idle Percentage |
Sum of long idling duration of the respective site’s assets ÷ Sum of the total duration (working + idle) * 100. Long idle is defined as asset engaged in idling with no movement for more than nine minutes. |
|
Medium Idle Percentage |
Sum of medium idling duration of the respective site’s assets ÷ Sum of the total duration (working + idle) * 100. Medium idle is defined as asset engaged in idling with no movement for more than six to nine minutes. |
|
Short Idle Percentage |
Sum of short idling duration of the respective site’s assets ÷ Sum of the total duration (working + idle) * 100. Short idle is defined as asset engaged in idling with no movement for more than three to six minutes. |
|
Productive Idle Percentage |
Sum of working idling hours of the respective site's assets ÷ Sum of the total duration (working + idle) * 100. Working idle is defined as asset engaged in idling with no movement for less than three minutes. |
|
Total Idle Percentage |
Sum of idling time (productive + short + medium + long) of the respective site’s assets ÷ Sum of the total time (working + idle) * 100. Idle time is defined as asset engaged in idling with no movement from less than three minutes to more than nine minutes.
|
|
Runtime |
Runtime |
Total running duration of an asset. |
Working Time |
Total duration the asset was working. |
|
Distance |
Distance |
Total distance traveled by an asset. |
Distance/Cycle |
Total distance traveled by an asset during a cycle. |
|
Working and Idle Fuel Burn |
Fuel used by an asset on a site. |
|
Fuel Burn Rate |
Fuel burned by all the assets on a site ÷ Maximum site operation time. Example: In a site, if Asset 01 burns 150 gallons and works 9:00AM-12:00PM (3 hours) and Asset 02 burns 150 gallons and works 12:00PM-3:00PM (3 hours), the fuel burn rate will be 50 gal/hr or 300 gallons (the total burned by both assets) divided by six hours (the time at least one asset was operating, i.e., 9:00AM-3:00PM) |
|
Idle Fuel Percentage |
Sum of idle fuel burned ÷ total fuel burned of all the assets in respective site * 100. |
|
Sum of all fuel burned for the assets during long, medium and short idling hours in respective site for the selected date range and asset tag. |
||
Total Fuel Burn |
Sum of all fuel burned during working, productive and substates (long, medium and short) idling hours in respective site for the selected date range and asset tag. |
For Legacy Assets
KPI | If Supporting Data Available | If Supporting Data Not Available |
Operational Time | Working + Idle | Total Working Time |
Total Runtime Area | Working + Idle | Total Working Runtime |
Total Duration | Working + Idle | Total Working Duration |
Total Fuel Area | Working + Idle | Total Fuel Burned |